Media Releases

Latest Releases

Climate Change

Land Clearing

Marine & Coastal

Mining

Other

Uranium & Nuclear

Climate Change

Line

Home » Latest Media Releases

» Climate Change » Land Clearing » Marine & Coastal » Mining » Other

Line

» 2005 » Archives: 2004 » 2003 » 2002 » 2001

5 April 2004

Alcan Gove Alumina Refinery Expansion Project

Draft Environmental Impact Statement – Main Report

A Submission by the Environment Centre NT: 5 April 2004

The Environment Centre of the Northern Territory recommends against approval for the Alcan expansion.

As indicated below we make this recommendation for many reasons including the lack of clarity as to what is actually being proposed and may be approved, and our great concern over the route of the proposed new gas pipeline with potentially serious impacts on high conservation value areas such as the Daly River and the Arafura 'Swamp'.

»

It is difficult to assess the EIS in isolation from the other components of the project i.e. the Trans Territory pipeline and the Blacktip Gas processing installation at Wadeye (which are currently at earlier stages of the environmental approvals process). The cumulative impacts of all three related projects should be assessed together before a final decision on approval for the refinery expansion is made.

»

ECNT is concerned that environmental approvals are being sought before a Definitive Feasibility Study is completed. The DFS, due by mid-2004, will include a detailed examination of the design, implementation, risk assessment and cost evaluation of the expansion (ES-1). There is every reason to suppose that significant changes to the project may occur as a result of the DFS. It is therefore even more difficult to assess what is essentially an interim EIS.

»

The EIS consistently maintains that the environmental footprint of the expansion will not increase, as it will occur within the existing lease area (apart from the construction of the workers' accommodation).

Yet it is acknowledged in the EIS that additional residue storage areas outside the existing leases may be required in the future due to the increase in total waste (the production of red mud waste, for instance, will climb from 1,674,000 tonnes per annum to 2,691,000 tonnes per annum).

Furthermore, the existing Residue Disposal Area has already had a significant impact upon vegetation communities in the vicinity of Pond 5 (15.2.5.1) due to increases in levels of salinity.

It is therefore not sufficient for the proponents to say that separate environmental approvals will be sought if additional storage areas are needed, then to use this as a justification for not discussing the potential environmental impacts in this EIS, as it appears more than likely that the additional areas will be required.

Back to top

»

No quantification of the amount of currently lost and spilled product (bauxite, hydrate and alumina) is made in Section 7.3.1.2. The EIS does say that modifications to one conveyor reduced hydrate spillage by an estimated 2,500 tonnes per annum. This seems to suggest that the amount of spillage is high. With increased throughput of materials in the expanded refinery, will spillage increase? This question is not addressed by the proponents.

»

There will be a significant increase in water consumption by the expanded refinery requiring seven new bores be drilled. Overall average water consumption is predicted to increase by 25%. Predicted groundwater levels in Observation Bore 1 will be 10.4 m MBHD (Melville Bay Height Datum), which is not far above the critical threshold level of 10 m MBHD. Any level below 10 m and the discharge of water to Yirrkala Creek is below the permitted minimum rate of 50 L/s (5.1.8.2).

 

More information about the potential ecological effects of lower discharge rates into Yirrkala Creek and Yirrkala Lagoon is required. It is not sufficient to say that on the previous two occasions that the level dropped below 11 m MBHD no observable impacts were noted in Yirrkala Lagoon.

 

The increased groundwater extraction will be continuous over a much longer time period. Moreover, groundwater levels and discharge rates could well be affected by altered rainfall conditions associated with climate change.

»

It is disappointing that Sulphur Dioxide emissions from the refinery will increase under a fuel oil scenario (Table 8.5.1), whilst the incidence of small dust particles will remain at similarly high levels at the Aboriginal community of Galupa no matter whether fuel oil or gas is used (Table 8.7.1). Carbon monoxide levels will also increase by a factor of three if gas is adopted.

»

In Section 9.1. the EIS claims that Alcan has reduced its company-wide greenhouse emissions by 1.1 million tonnes CO2e, or 5% from 1999 levels on a 'growth adjusted basis', without explaining what this term means. It is therefore hard to evaluate Alcan's claims of greenhouse efficiency. ECNT has concerns about the environmental impacts of the refinery expansion if fuel oil continues to be the primary energy source for the power station.

 

This will result in a much higher level of greenhouse emissions, increasing by approximately 1.38 million tonnes per year. Even if natural gas is used emissions will rise by approximately 595,000 tonnes per year. It needs to be pointed out that it is the total quantity of emissions that this project should be assessed on, not the amount of emissions per tonne of alumina produced. The atmosphere and climate system is ultimately indifferent to alumina production efficiencies.

»

The EIS admits that Melville Bay in the vicinity of the Residue Disposal Area and the refinery can be described as a 'slightly to moderately disturbed ecosystem' (13.3.1). Nabalco's 2001 Safety, Health and Environment Report indicates that median vanadium levels in this area in 1999 exceeded the ANZECC water quality guidelines and were only slightly below guideline levels in 2000 (p26).

 

The expanded refinery, according to the EIS modelling, will produce similar levels of vanadium and other metal concentrations in its water discharges. ECNT's concern is the cumulative impacts of these continued discharges on the marine ecosystem and the species that inhabit it.

 

There is already an area of approximately 70 hectares where no macro-invertebrate fauna can be found (14.3.2.1). The cautious wording in the EIS demonstrates that there is still scientific uncertainty as to the factors which are causing the dearth of macro-invertebrates.

»

The impact upon turtles, a threatened species, is not assessed in sufficient detail. It is clear that no formal turtle survey has been completed in the impact zone (14.3.2.3 & 14.5.3).

 

Moreover, there will be a much greater risk of heavy fuel oil spills into the marine environment if gas is delayed (14.5.1.2).

Back to top

»

The discussion of the flora and fauna surveys demonstrates that habitat quality within the refinery and residue disposal areas has already been significantly degraded by human activities and feral animals (15.3.7.1) and that the impacts will continue.

 

It is perhaps a sad reflection upon the refinery's current environmental impacts that a listed vulnerable species like the northern hopping mouse has not yet been located in the vicinity of the refinery (even though there is suitable habitat).

»

It is disappointing that in the account of Yolngu history (20.2.1) there is no mention of the fact that the original mine was imposed upon the Yolngu people against their wishes. Nor is there any mention of significant protest events such as the bark petition in 1963, or the 1971 Gove Land Rights case heard by Justice Blackburn in the Federal Court.

»

The social impact assessment is very superficial and one-sided, in our opinion. In Section 21.5 there is no mention of any detrimental impacts of the existing mine, yet it is obvious that the Aboriginal communities of the area have been impacted by more than royalties and business opportunities. Along with the mine came a large influx of non-Aboriginal people, a town, additional access to alcohol and so on. It is clear to ECNT that the community consultation processes have been deficient.

 

This is best illustrated by the fact that only 8 responses were received from the first feedback form and 6 from the second form sent out by the consultants to the wider community. The EIS does not indicate how many members of the public were interviewed aside from these written responses. There is no attempt to distinguish between the feedback received from Yolngu people and organisations and that of the non-Aboriginal community.

 

There has been no direct consultation with Yolngu apart from through the Reference Group. There is also insufficient detail on the potential impacts on the nearby Galupa Aboriginal community (apart from noise, air quality and lighting effects).

»

ECNT was also somewhat perplexed to discover that Table 23.6.2 (23-15) indicates that we raised not one single issue during the initial meeting with Alcan representatives in April 2003. This is not an accurate reflection of the content of the meeting and raises serious questions about both Alcan's listening and note-taking ability and the usefulness of including in the EIS such a broad-brush summary of issues raised during stakeholder consultations.

In short, Table 23.6.2 smacks of tokenism.

Line

For more information on Climate Change contact ECNT:
Phone: 08 8981 1984
Email: ecnt@octa4.net.au

 

Back to top

 

 

 

About the ECNT » Current Campaigns » What's New » Media Releases
Newsletters » Search/Useful Links » Membership » Contact Us » Home

 

 

 

The Environment Centre of the Northern Territory
3/98 Woods St, Darwin » Postal Address: GPO Box 2120, Darwin 0801 NT
Phone: 08 8981 1984 » Fax: 08 8941 0387 » E-mail: admin@ecnt.org